Requirements and Acceptance Criteria Are Critical


Over the past few months, I have worked on a project with precious few requirements and no acceptance criteria. Essentially the dictate is done means “keep coding until I say it is fine”. The problem is this insanity never ends, as changes are placed into queue before the coding is “done”.

There are a few myths I have seen in action in various businesses. Here they are with the reality following:

  • Agile means loose requirements and very little documentation – This is false. Actually Agile needs requirements and documentation as much as any other methodology, the requirements are just stated in the form of a user story and some of the documentation is in the form of unit tests.
  • Business needs to be fluid, so we should not tie down “done” with a firm set of criteria – In reality, you need to define done as explicitly as you can. You may change (request) the definition over time, but a developer without a clear path is as likely to code away from the solution as code towards it.
  • Hire a bunch of really smart developers and you can get around firm specifications and acceptance criteria – While very smart developers are faster at coding their way out of a hole, and less likely to code inescapable holes, there was only one real miracle worker that ever walked the face of the earth … and it is not your developer.

    NOTE that really smart developers often over-engineer or over-complexify solutions when left to their own designs.

We keep trying to view planning (with its outcome of requirements and a definition of done) as an optional exercise. This is generally done in the name of time, but how much time is blown having a developer rewrite code? In my experience, not defining what is being built has always turned out more expensive than spending time up front to plan. If you are truly overloaded, rather than avoid planning, you should force planning. Otherwise, you will spin at the end of the project, trying to “plan” after development, which means figure out how to get the code to do what I want with the least amount of hours. This is an exercise is low quality and relies on a lot of luck.

A couple of things I have noticed in my career:

  • “Do everything this {website} does in a {mobile application} is not a requirement (you can change the {} types for your situation, if you like). As much as you might think it is a requirement, what is being done is up for interpretation, even if the basic business rules are the same, and the developer’s interpretation and yours are as likely to be different than they are to be the same. This is especially true when moving from one form factor (ex: web to mobile) or coding paradigm to another (ex: webforms to MVC).
  • “Code this until I am happy with it” is a recipe for disaster. While it leaves a lot of flexibility for the person who wants to be “happy” to massage the outcome, it causes badly bolted on code as new rules are manufactured. In the lucky cases, the code can be refactored to some level of quality, but this is more of an exception than a rule. Ouch!

Let’s take a quick example I can think of lately. The requirement, as loosely stated, was put together a tree of categories for eCommerce and append products to the tree. Then create a detailed file for the products. The acceptance was “I will let you know when it is right”. Here is part of the history:

  1. Add categories from another source
  2. Exclude some categories
  3. Replace images found in data source with a dictionary of categories and images
  4. Use a template to create a tree where none existed and append to a specific spot in the tree
  5. Create a featured products file
  6. Append that file to a specific node in the main tree file
  7. Exclude categories with no children or products
  8. Scrub HTML for certain nodes in the XML document, replacing many of the characters with HTML escape sequences
  9. Search for certain “illegal XML characters” and replace them (if acceptance criteria were built, it might have been as simple as convert from UTF-8 to UTF-7 – live an learn?)
  10. Do a binary scrub of characters not caught with the loose ruleset in #9

All in all, numerous hours (weeks?) were burned due to the lack of planning on many levels, equating to tens of thousands of dollars. If this is the rule in the organization, and you add all of the projects up, how many hundreds of thousands, perhaps millions, of dollars is the company burning through that could be avoided by setting down requirements and a definition of done?

What if requirements change during development? If this is not the best reason to use Agile methodologies, I don’t know what is.But, even if you use waterfall, you stop development on the feature(s) in question and refine the requirements before moving forward. To either a) let the development continue or b) continue altering output until “happy” is like dining in a really crappy fine dining establishment … a lot of money for a really bad meal.

The point here is you can’t plan a trip without knowing where you are going. By the same token, you can’t build an application without knowing what done looks like.

Peace and Grace,
Greg

Twitter: @gbworld

Why Planning is Important


I have been working on a project for quite some time that is considered time sensitive. Due to the time sensitive nature, actually creating full requirements and acceptance criteria is considered frivolous, so the concept is code and verify, based on some unknown standard. It is not quite that bad, but when someone (generally me) argues for planning, I am told the following are equally valid ways of approaching development for this project.

  1. Creating requirements and acceptance criteria (i.e. planning) and then coding to match the requirement and acceptance criteria.
  2. Coding based on a loose, one sentence, “specification” and then fixing issues based on User Acceptance testing.
  3. In short,  the group has opted for a “show me what you have and I will then tell what is wrong with it” versus “tell me what you want and I will show you what you have told me you desire”. While we ultimately end up with the same product, I disagree these are “equally valid ways” of developing a new application.

To illustrate this, think back to your last vacation. If you have not had one in a long time, you should go on one soon, but if you can’t imagine your last business trip. It went something like this:

You woke up at some time during the day (or night) and packed enough clothes for a week’s worth of time. Your spouse and children did the same thing. You then got in the car and drove to the airport and stated to the ticket agent “I have $1500 to fly and 4 people, so I need whatever ticket is the closest to $375 per person for a round trip”. Once you had your tickets, you got on the plane and flew.

When you landed, you went down to the car rental agencies and got a car, using the same logic. “I have $500 to spend on a car, so give me whatever car I can get for a week with that much money.”

You then drove off out of the airport and got on the road whichever direction fit your whim and drove until you found a hotel that seemed to be within your budget. You went up and got a room.

Once in the room, you looked at the local guidebook and figured out what types of things you could do in this town with the amount of day you had left and went out and had fun.

Does this sound even remotely like your last vacation (or trip)? No? Why not? Well, if you are a normal person, you can see all types of problems with this. Here are a few:

  1. What if $250 only buys a ticket to Idaho, in the middle of winter? Did you pack for snow or the beach?
  2. What if you can’t find a flight with 4 tickets available?
  3. What if the car rental agency does not have a car that fits your budget?
  4. What if the hotel does not have rooms available?
  5. What if the town you landed in has nothing you are interested in seeing?

I am sure I can think of more, but the point is that you would not schedule a vacation out of town without some idea of where you were going to go and where you were going to stay, right? But you would be this careless with a “mission critical” project?

There is a belief in some circles that not knowing everything about the final product means you should not nail anything down. To me, this is about as stupid as stating “I can’t book a room at the Hilton for our vacation because I am not sure what I am going to order for breakfast, lunch and dinner every day we are on vacation”. Yes, there are some parts of the project you may not be able to figure out right now, but not planning anything as a result means you are going to, at best, spend a lot more time (i.e. money) to develop the product.

What has happened on my current assignment is I am now getting back pieces to fix. They are logged as defects, but without a criteria of what is right, nothing, outside of failure to work, is really a defect. And, since there is no criteria, “defects” are being found in serial. Take one step forward, find a “bug”, fix that one bug. Rinse. Repeat until all the “bugs” are washed out. The biggest issue here is we can, with any confidence, state when the final product is going to be ready for release, as there is no firm definition of what done looks like.

This topic has been covered as nauseum, of course. Steve McConnell has some interesting insights in his book “The Project Software Survival Guide”, which I think should be mandatory reader for every manager that needs IT work done.

From McConnells’ company site, I have found a couple of neat gems from his book. The first talks about when a defect is created and how much it costs to correct. This is shown below.

If you do not have time to write requirements and work out the architecture and design, every defect is a requirements defect. Pretty expensive proposition, yet this is precisely what is being done.

Here are a set of images from Steve McConnell’s own site that describes perception versus reality. Management often believes this is the optimal development path:

They accept that there is a certain amount of unproductive time (meaning time not moving forward towards the end of the project, whether reworking bad code or going to get coffee), but they don’t want the burden of planning, which is seen like the picture below:

If I get rid of the planning (process), I end up with more productive time. The problem is the reality looks more like this:

Without proper planning, what started as a small amount of thrashing, ends up consuming a huge amount of time, as more and more “defects” are discovered and more and more code has to be reworked based on differing understandings of what is acceptable and what done look like. In addition, more and more time gets consumed in process, including planning how to get from “what we now have” to “what is acceptable. One thing missing from this diagram that is present in the book is the dot just before process and thrashing consume 100% of daily efforts. That dot indicates the luck projects that get released before all of the participants drown in the sea of non productivity.

The ideal situation is enough planning to understand both what done is and how to determine each feature is acceptable to fit that picture of done. This is shown in the final graphic linked from McConnell’s site.

In short: planning works. If you want to read McConnell’s entire treatise on this topic, click here.

My next topic, which I will post in a few days, will cover why “hiring rock stars” is not an adequate alternative to proper planning.

Peace and Grace,
Greg